METHOD STATEMENT FOR CONTROLLED BLASTING WORK
METHOD
STATEMENT FOR CONTROLLED BLASTING WORK
|
SR. No. |
TITLE |
|
1 |
INTRODUCTION |
|
2 |
SCOPE OF WORK |
|
3 |
REFERENCES AND STANDARDS |
|
4 |
TOOLS / TACKELS AND MACHENIRIES |
|
5 |
MATERIALS AND SPECATIONS |
|
6 |
REQUIERD MANPOWER AND RESPONSIABILITY |
|
7 |
SHORT NOTE ON BLASTING |
|
8 |
PROCEDURE |
|
9 |
QUALITY ASSURANCE |
|
10 |
DOCUMENTS |
|
11 |
SAFETY |
|
12 |
AREA OF APPLICATION |
1. INTRODUCTION:
This method statement describes the work
procedure to be followed for controlled blasting work on required location at
Joy project.
2. SCOPE OF WORK:
The scope of work involves the following: Drilling of
holes, stemming, filling of explosives, completion and checking of circuit than
conduct a controlled blasting operation by covering the circuit by rubber mat.
3. REFERENCES AND STANDARD:
This document should be read in conjunction with IS
4081, occupational health and safety act SNS 1996, Blasting safety regulations
under section 82 and explosive blasting rules 126 of 2008 and BOCW act for
execution of work at site.
4. TOOLS/TACKELS AND MACHINERIES:
Measuring tape, Tractor
mounted Air compressor, Jack hammer, drilling rods, Hose pipe, Nitrate mixture,
Electric detonators, short delay detonators, rubber mat, wooden stick, OHM
meter, exploder, permanent blasting wire, Explosive van, magazine, storage,
transport, and use license.
5. MATERIAL AND SPECATIONS
FOR BLASTING:
Explosive (nitrate- Make-SOLAR super power 90,
125 grams, dia- 25 mm), detonators ( Make- Solar) and blasting caps etc.
v Depth= 1.50 mtr to 3.00
mtr
v Hole diameter = 32 mm
v Cartridge / bulk
explosive to charged per hole = as per required or 2 to 5 cartridge approximate
v Powder factor = 200
GRAMS OR AS PER REQUIREMENT.
v Weight of Rubber mat
shall be 1800 – 2000 kg min
v No of Blasting rows = 2 nos
v Spacing between holes =
1.2 mtr
v
Burden
= 1.00 mtr
v
Calculation for powder
factor is – PF=
Avg 3 nos of cartridge in grams. / (depth of hole x spacing between holes x
burden) =(125 x 3 ) / (1.5 x 1.2 x 1) =
375/1.8 = 208 grams.
6. REQUIERD MANPOWER AND
RESPONSIABILITY:
|
Execution Engineer/Supervisor |
01 no. |
|
Safety Engineer/Safety Steward |
01 no. |
|
Labors (Skilled& Unskilled)
(Skilled- Short fire license Holder, tractor driller) |
As per requirement |
a.
Project Manager shall be overall
responsible for :
Ø Safety
Ø Quality
Ø Timely completion of the job.
b.
Construction Manager shall be
responsible for :
Ø Implementation of Method statement.
Ø Overall safety, quality &
progress.
Ø Deputing Engineers/Supervisors as
per requirement.
Ø
Arranging
all required resources to carry out the job and Preparing documents, reports
for submission to Consultant/ Client.
c.
HSE Manager shall be responsible for
:
Ø
All person
related to blasting activity shall be inducted by safety person.
Ø
Day to day
activity shall be monitored.
Ø
Legal
requirements, license, blasting permission shall be checked / verified.
Ø
JSA/HIRA
shall be prepared.
d Site Engineers/supervisors shall be
responsible for:
Ø Identify the location for blasting.
Ø
Allotment of
resources.
Ø Compliance with this procedure and relevant
project specified requirements.
Ø Notify to construction managers after
completion of blasting activity.
Ø Coordinating with store, P & M, Safety
department.
Ø Taking safety measure necessary to ensure
safety of all personnel involved.
e Site P&M Engineer shall be
responsible for:
Ø
Ensuring all
machineries in working condition.
Ø Care shall be taken by the operator
of all machineries to avoid any injury to workers.
Ø Inspection of all machineries shall
be done prior to the work.
Ø
Ensuring
Proper inspection & maintenance of machineries whenever required or suggest
to the vendor.
7. SHORT NOTE ON BLASTING:
Method of blasting
includes first step of drilling a number of holes at predetermined angle in a
horizontal angle cut pattern or in a vertical angle cut pattern about the
central zone of a working face, drilling a number of parallel cut hole within a
projective area of the above mentioned slant hole; loading shock tube in the
slant holes and an explosive material by indirect priming in the parallel cut
holes up to the bottom of the slant holes; blasting the slant holes to form a slant
free surface; blasting a center cut hole out of the parallel cut holes to form
two free surfaces having a funnel shape; and sequentially blasting a middle cut
hole and an outer hole out of the parallel cut holes to form a cubical space
Controlled Blasting
Services is very proud of its safety record. When using explosives there are three
main criteria to consider -
(a)Ground vibration
(b)Fly Rock
(c) Air Blast
Surface Blasting Services moves onto site with our
drilling equipment. The burdens and spacing of the drill holes will vary
according to the depth of the holes and the type of blasting to be done i.e.
trenching, road cutting, boulder blasting etc. The holes will be marked by a
qualified blaster who will also supervise the drilling. After all the drilling
has been done we will obtain blasting and transport permits from the SAPS. We
inform the Inspector of Explosives the amount of explosives to be used and the
distance from the explosive magazines (place where explosives are stored) to
the blast site. The vehicles used to transport explosives have to comply with
the specifications set down in the Explosives Act. The vehicles are equipped
with 9kg DCP lire extinguishers which are inspected monthly. On the day of the
blast, the blaster with his permits, will draw explosives and proceed to the
blast site. The explosives are carried in special locked up aluminum boxes. On
site the blasting boards will be placed around the blast area. The blaster will
then charge up the drilled holes.
GROUND
VIBRATION
When
blasting close to private property the maximum peak particle velocity is 25mm
per second. Example – a house 15 meter from the blast, we are allowed 4.5kg of
explosives between each 25mm second relay. One stick of explosives 25 x 200
Energex weighs 0. 11 kg, therefore you are allowed 40.90 sticks between each
relay as to be within the limits of 25 mm per second.
By using this method there would be no damage to private property. Should the
contractor require a vibro recording to be done, we will employ an independent
company to set up monitoring equipment to the nearest house from the blast
area. The cost of the vibro is for the contractors account.
FLY
ROCK
There are two methods to curtail fly rock. One is by
placing rubber blasting mats on the blast area. The other is to place sand on
the blast area to a depth left to the discretion of the blaster.
AIR
BLAST
The detonating fuse on the surface of the blast
detonates at 22000 Feet per second thus causing air blast. The way to curtail
the air blast is to cover the surface detonating fuse with sand. Once the blast
has been charged up the blaster will then send his staff with red flags to
remove all persons and animals to a safe distance. The blaster will then
personally visit the flagmen to ensure the area is safe. He will then attach
the detonator to the detonating fuse. The blast is set off by an electric shot
exploder attached to a blast cable, a safe distance from the blast. The blaster
will only fire the shot once he is satisfied that the area is safe and has
contact with all his flagmen. Once the shot has been fired the blaster will
then visit a blasted area to check that all the shots have gone off. Once he is
satisfied he will then declare the area safe. No storage of explosives is
permitted on the site.
8. PROCUDURE:
1.
Lineout of
co-ordinates/grid lines of respective areas to blasted as per available free
face at site.
2.
Study of soil
investigation reports & specification received from client.
3.
All underground cables
are removed off with respective authorities before planning the blasting work.
4.
Taking out and recording
of OGL’s.
5.
All safety procedures and
safety checks should be complete before starting the work.
6.
Blasting of area as per
given marking by drilling holes with tractor compressor & Jackhammer
7.
The holes are then
charged with nitrate mixture and detonators as per requirement.
8.
The remaining part of the
hole is stemmed using sand with the help of wooden stick.
9.
Surface connection of all
the holes is conducted and circuit is checked for continuity in presence of
Blaster.
10.
The holes will then be
covers with a Rubber mat (1800 kg to 2000 kg) and will be loaded with sand bags
or tyres for carrying out controlled blasting.
11.
Area evacuation will be
carried out before actual blasting is to be carried out with the help of
flagman.
12.
The Exploder will be
placed at a distance of minimum 10 to 50 mt from blasting location and after
clearance from responsible teams / signal man, blasting will be carried out.
13.
Once blasting is carried
out immediately after 5-10 minutes area is inspected for misfires and area
clearance is given once approved by blaster.
14.
If a misfire occurs the
misfire process will be followed to remove the misfire.
15.
Ensure the blasting is
proceeding as per given line out and up to required depth or as directed.
16.
Mucking of the blasted
material is to be done by attaching a bucket as.
17.
Dewatering is to be done
in case of occurrence of ground water.
18.
The working space should
be sufficient for labourers to stand and move around in. Safe working
conditions should be followed and enforced.
19.
Final cleaning of the
excavated surface is tobe done manually.
20.
All required levels are
recorded in JMR which is given to the client and contractor representatives
before starting the blasting work and at the end of each milestone.
Special care to be taken
in case of Misfire
1)
A
careful search for cartridges and detonators shall be made in the presence of
the shot fire,
Amongst
the material brought down by the shot.
2)
As
far possible,the search for the detonator and cartridges and the loading of any
coal,stone or debris that may contain a detonator,shall be carried out without
the aid of tools.
3)
A
misfire hole, which cannot be dealt with in the manner so prescribed, shall be
securely plugged with a wooden plug.
4)
When
a misfire shot is not found or relived, the shot firer shall give information
of the failure to concerned official who
may relived or take over charge from him.
5)
The
shot firer of the next shifts shall locate and blast the misfired hole after a
thorough
Examination of the
place, where the misfire was reported to have occurred. If he is satisfied that
no misfire has actually occurred may permit drilling.
9. QUALITY ASSURENCE:
· Assurance of approved methods and
materials are being used and conformance of the specifications while execution
· Inspection and monitoring of work.
· Incoming material inspection and
review certificates.
10. DOCUMENTS:
Ø Register of Blasting
Ø Copy of
Licenses
Ø Explosive License
Ø Transport of Explosive in Road Van
Ø Shot Firers License
Ø Annexure 1
Ø MSDS
of following material shall be available in safety department
1)
short delay electronic detonator,
2) super power 90
11. SAFTEY:
Controlled blasting
·
valid
competency certificate to carry out blasting
·
Permission
of government authority
·
Use
of mandatory ppes, Safety shoes, helmet, R jacket, Ear muff/plug, hand gloves,
Nose mask, safety goggle etc
·
200
mtr area clear before blasting work
·
Valid
compressor & tools tackles third party test certificate
·
Signal
manrequired.
·
Close
supervision
·
Work
during 6.00 am to 6.00 pm
·
Explosive
vehicle remove from site after day work completed,
·
Storage
of explosive not allowed in premises
·
Wooden
stick use for charging operation
·
Mobile,
match box, not allowed while handling of explosive material
·
Fire
extinguisher ABC type
·
TBT
before start of work and Inspection of blasting hole before & after
blasting by competent person with
· Hard barricades will be
provided around the work area in case of deep excavation area and in the area
of vehicular movement respectively.
· Entry to the basement /
footing level will be restricted for the access.
· Vehicular movement will
be strictly restricted.
·
Safety
sign / Warning sign boards will be provided around the blasting work area.
12. AREA OF APPLICATION:
At footing level of all building