Introduction :
Safety concept is very unique, interesting, more simple & dangers depend about you…
Today we have shared the most important topic for the site Safety
plan, EHS plan, HSE plan concept is the same only deferent the name.
Site Safety Plan of the Contractor- Prescribed Contents
(Note: - The safety plan should be prepared in line with the contract
safety requirements)
|
|
|
|
Site Safety Plan of Contractor M/s…………………… |
||
|
|
|
|
|
|
|
|
Sr. No. |
|
|
Required Contents |
||
|
1 |
Introduction |
|
|
||
|
|
Project Highlights, |
|
|
||
|
|
|
· |
Name of Project |
|
|
|
|
|
· |
Location |
|
|
|
|
|
· |
Client |
|
|
|
|
|
· |
Architect |
|
|
|
|
|
· |
Structural designer |
|
|
|
|
|
· |
PMC |
|
|
|
|
|
· |
Contractor |
|
|
|
|
|
· Start Date of Project |
|
|
|
|
|
|
· Period of the Project |
|
|
|
|
|
|
· |
Scope of work |
|
|
|
|
|
· |
Project cost |
|
|
|
2 |
EHS Objectives & Targets for Project |
|
|
||
|
|
EHS Objectives & Targets agreed between client organization
& contracting organization should be clearly |
||||
|
|
described |
|
|
||
|
|
For Example: |
|
|
||
|
|
|
Objectives |
Target |
|
|
|
|
|
Implementation of Site safety plan |
100% |
|
|
|
|
|
Induction of employees |
100% |
|
|
|
|
|
PPE provision |
100% |
|
|
|
|
|
Medical Examination of employees |
100% |
|
|
|
|
|
Fall protection barrication & safety
nets |
100% |
|
|
|
|
|
Electrical Safety (IP-55 & 30mA ELCB) |
100% |
|
|
|
|
|
Dust & Noise pollution monitoring & control |
100% |
|
|
|
|
|
Illumination level as per standard |
100% |
|
|
|
|
|
Comply with legal rules and regulations |
100% |
|
|
|
|
|
Note: Contractor may include appropriate objectives and targets as per
their company policy. |
|
||
|
3 |
Project Layout plan mentioning Emergency Assembly
Points, Fire Points, Store, first-aid center, induction |
||||
|
|
center, canteen, restrooms, drinking water point, sanitation, tower
crane, batching plant, etc… |
||||
|
|
|
|
|
||
|
4 |
EHS Policy |
|
|
||
|
|
|
|
|
||
|
5 |
Vision statement |
|
|
||
|
|
|
|
|
||
|
6 |
Definitions & Abbreviations |
|
|
||
|
|
|
|
|
|
|
|
7 |
Safety Organisation: |
|
|
|
||||||||
|
|
|
· |
Site Organogram including Safety Organisation |
|
|
|||||||
|
|
|
· |
Corporate safety organogram |
|
|
|
||||||
|
|
|
· |
Safety resources qualification & competency criteria |
|
|
|||||||
|
|
|
|||||||||||
|
8 |
Role & Responsibility of PM/CM/Tower or
Area In-charge /Site Engineer/Supervisors/Safety Manager/Safety |
|||||||||||
|
|
|
officer/ Safety Supervisor/Safety Steward/ Corporate safety Head/
Admin In-charge/labour camp |
||||||||||
|
|
|
boss/Store In-charge/ Quality In-charge/P&M In-charge/Sub Contractors/Workers/Security/
Vendors- |
||||||||||
|
|
|
Suppliers-Transporters /Other site Employee
/ Project EHS Committee |
|
|
||||||||
|
9 |
Project EHS Committee |
|
|
|
||||||||
|
|
|
· |
Formation of Project EHS Committee |
|
|
|
||||||
|
|
|
· |
Agenda |
|
|
|
||||||
|
|
|
· |
Workers and sub-contractors participation in committee |
|
|
|||||||
|
|
|
|
|
|
||||||||
|
10 |
Safety Budget for EHS |
|
|
|
||||||||
|
|
|
· |
Safety Consumable items |
|
|
|
||||||
|
|
|
· |
Celebration of special days / weeks |
|
|
|
||||||
|
|
|
· |
External Awards nominations fees / charges |
|
|
|||||||
|
|
|
· |
Non-consumable items |
|
|
|
||||||
|
|
|
· |
Fire protection items |
|
|
|
||||||
|
|
|
· |
Safety infra |
|
|
|
||||||
|
|
|
· |
Awareness Programs |
|
|
|
||||||
|
|
|
· |
Motivational programs |
|
|
|
||||||
|
|
|
· |
Miscellaneous |
|
|
|
||||||
|
11 |
List of Major Plant & Machinery and
deployment schedule with history card. |
|
|
|||||||||
|
|
|
|
|
|
||||||||
|
12 |
Safety Infra: |
|
|
|
||||||||
|
|
|
Induction Room, Safety Park, Vertigo test platform, scaffold
mock-up. |
|
|
||||||||
|
|
|
Logistic Infra: |
|
|
|
|||||||
|
|
|
Occupational Health Centre, Induction
Centre, Canteen, Rest Rooms, material store, fuel storages, fencing / |
||||||||||
|
|
|
boundary, drinking water, Lavatories, security check posts,
ambulance/ dedicated emergency vehicle etc... |
||||||||||
|
|
|
(as per logistics plan) |
|
|
|
|||||||
|
13 |
EHS Legal Requirements |
|
|
|
||||||||
|
|
|
· |
Identification of applicable legal & other requirements |
|
|
|||||||
|
|
|
· |
Legal Register – Quarterly Audit & Update |
|
|
|||||||
|
|
|
· |
Safety Contractual Requirements (attach a annexure to site safety
plan) |
|
|
|||||||
|
|
|
· |
Submission of EHS returns to authorities |
|
|
|
||||||
|
14 |
Hazard Identification & Risk Assessment
(HIRA), Communication & Deployment of controls |
|||||||||||
|
|
|
· |
Purpose |
|
|
|
||||||
|
|
|
· |
Risk assessment team |
|
|
|
||||||
|
|
|
· |
Identification of activities and hazards |
|
|
|
||||||
|
|
|
· |
Risk Assessment Matrix |
|
|
|
||||||
|
|
|
· |
Risk Control Table as per Risk Assessment Matrix |
|
|
|||||||
|
|
|
· |
Severity Table of Hazard |
|
|
|
||||||
|
|
|
· |
Probability Table(Likelihood of Occurrence) |
|
|
|||||||
|
|
|
· |
HIRA approval hierarchy |
|
|
|
||||||
|
|
|
Note : The final approval for HIRA is
mandatory from Client/ PMC |
|
|
||||||||
|
15 |
List of Activities and Method Statements and
Generic risk assessment |
|
|
|||||||||
|
16 |
Environment Aspect Identification,
Communication & Deployment of controls |
|
|
|||||||||
|
|
· |
Identification of Environmental Aspects and determining Impacts |
||||||||||
|
|
· |
Communication of Environmental Aspects and Impacts |
||||||||||
|
|
· |
Determining & deploying controls (engineering, administrative
& personal) |
||||||||||
|
|
Environmental Monitoring |
|||||||||||
|
|
· |
Availability of resources, process and frequency of Environment
Monitoring (Air Quality, stacks, |
||||||||||
|
|
|
Water Quality, Noise, illumination etc.) |
||||||||||
|
17 |
Work Permit System |
|||||||||||
|
|
· |
Purpose |
||||||||||
|
|
· |
Permit approval flow chart |
||||||||||
|
|
· |
Identification of activities for permit applications |
||||||||||
|
|
· |
Permit Formats for: Excavation
Work /Confined Space/ Hot Work/Height Work/ Night Work/ |
||||||||||
|
|
|
Permit for blasting operation/ Permit to
open manhole Cover / Cut -outs and lift shaft - Grills/ |
||||||||||
|
|
|
handrails/ safety net/hard barricading & Electrical-LOTO system,
Concreting Pour Card and Scaff- |
||||||||||
|
|
|
Tag. |
||||||||||
|
|
Note: The final
permit approval authority is Client/ PMC ( Refer SOP on permit to work system
of GPL) |
|||||||||||
|
18 |
General Safety Rules & Regulation |
|||||||||||
|
|
1. |
Do’s & Don’t ( Safety & health instruction ) |
||||||||||
|
|
2. |
Safety Signage’s; Posters; Safety Motivational
Scheme & Safety awareness display |
||||||||||
|
|
3. |
Visitor safety |
||||||||||
|
|
4. |
I-Card & Insurance |
||||||||||
|
|
5. |
Safety Induction |
||||||||||
|
|
6. |
Monthly Safety activity Planner for
contractor |
||||||||||
|
|
7. |
Safety Inspection & audit Schedule |
||||||||||
|
|
8. |
Portable Power Tools Safety |
||||||||||
|
|
9. |
Vehicle / equipment’s Safety (Inside &
Outside Project) |
||||||||||
|
|
10. |
Hazardous & flammable material safety [Gas cylinders (LPG; DA;
Acetylene)/Oil/Fuel/Paint & other |
||||||||||
|
|
|
lubricant] |
||||||||||
|
|
11. |
Use; Inspection; testing; maintenance & certification of Tower
crane/ Mobile crane /Material |
||||||||||
|
|
|
Hoist/Passenger Hoist/Gondola/floor Mounted
crane/lifting tools & tackles/ Batching Plant & other |
||||||||||
|
|
|
major Plant & Machinery. |
||||||||||
|
|
12. |
Operator of a crane, winch or other lifting appliance, transport
equipment or vehicle, signal man, |
||||||||||
|
|
|
technicians safety and competency |
||||||||||
|
|
13. |
Scrap /Waste Management |
||||||||||
|
|
14. |
Temporary structural approval Process |
||||||||||
|
|
15. |
MSDS |
||||||||||
|
|
16. |
Machine guarding |
||||||||||
|
|
17. |
P&M preventive maintenance plan |
||||||||||
|
|
18. |
Numbering and marking of floors/ levels |
||||||||||
|
|
19. |
Evaluation procedure of contractor / sub-contractor |
||||||||||
|
|
|
|||||||||||
|
19 |
SOP’s for Construction Activities |
|||||||||||
|
|
1. |
Piling |
||||||||||
|
|
2. |
Excavation |
||||||||||
|
|
3. |
Demolition |
||||||||||
|
|
4. |
Scaffolding & formwork |
||||||||||
|
|
5. |
Reinforcement |
||||||||||
|
|
6. |
Concreting |
||||||||||
|
|
7. |
Work at Height |
||||||||||
|
|
8. |
Material Handling & Stacking |
||||||||||
|
|
9. |
Ladder Safety |
||||||||||
|
|
10. |
Electrical Safety |
||||||||||
|
|
11. |
Hot Work (Welding & Gas Cutting) |
||||||||||
|
|
12. |
Erection & Dismantling ( Tower crane/ Mobile crane /Material
Hoist/Passenger |
||||||||||
|
|
|
Hoist/Gondola/floor Mounted crane/Batching Plant & other major
Plant & Machinery ) |
||||||||||
|
|
13. |
Lift shaft / cut out / edge barrication / safety net closers |
||||||||||
|
|
14. |
Facade |
||||||||||
|
|
15. |
MEP |
||||||||||
|
|
|
|
|||||||||||
|
20 |
General Controls |
|
|||||||||||
|
|
· |
Access controls-prevention of unauthorised entry & working |
|
||||||||||
|
|
· |
Housekeeping |
|
||||||||||
|
|
· |
Illumination |
|
||||||||||
|
|
· |
Smoking and alcohol Prohibition |
|
||||||||||
|
|
· |
Debris collection and disposal |
|
||||||||||
|
|
· |
Dust control & suppression |
|
||||||||||
|
|
· |
Sanitation & Hygiene |
|
||||||||||
|
|
· |
Traffic Management |
|
||||||||||
|
21 |
Fire Safety at site and labour camp |
|
|||||||||||
|
|
· |
Identification of fire prone area |
|
||||||||||
|
|
· |
Preventive measures |
|
||||||||||
|
|
· |
Protection Measures |
|
||||||||||
|
|
· |
Fire points |
|
||||||||||
|
|
· |
Hot work control measures |
|
||||||||||
|
|
· |
Prohibiting signage & instructions |
|
||||||||||
|
|
· |
Training & Mock drill |
|
||||||||||
|
22 |
Incident Investigation, Reporting Protocol
& Communication. |
|
|||||||||||
|
|
· |
Incident/Accident Recording, Reporting, Analysing and implementing
controls |
|
||||||||||
|
|
· |
Preparation of CAPA and related training |
|
||||||||||
|
|
· |
CAPA implementation |
|
||||||||||
|
|
· |
HIRA Review |
|
||||||||||
|
23 |
EHS Training |
|
|||||||||||
|
|
· |
Training set-up & training aid |
|
||||||||||
|
|
· |
Mechanism of identifying Training Needs and imparting training |
|
||||||||||
|
|
· |
Safety Training (Induction/Daily PEP TALK/ Job
Specific/General/Training/Special Training) |
|
||||||||||
|
|
· |
Training Calendar & Training Matrix (Trade wise)– deciding
contents & selecting trainers |
|
||||||||||
|
24 |
Health Surveillance, Medical Aids &
First Aid |
|
|||||||||||
|
|
· |
Arrangement and process of pre-employment and periodic medical
examination. |
|
||||||||||
|
|
· |
Arrangement and process of routine medical aid and emergency medical
aid. |
|
||||||||||
|
|
· |
Arrangement of first aid under dedicated male nurse as per BOCW and
contractual requirement. |
|
||||||||||
|
|
· |
Stretcher provision (minimum two) |
|
||||||||||
|
|
· |
Tie-up with nearby best hospital. |
|
||||||||||
|
|
|
|
|||||||||||
|
25 |
Labour Camp Management |
|
|||||||||||
|
|
· Setting of Worker Camp and approval
process. |
|
|||||||||||
|
|
· |
Toilets & Urinal |
|
||||||||||
|
|
· |
Drinking water facility |
|
||||||||||
|
|
· Inside and area illumination facility |
|
|||||||||||
|
|
· Electric supply & safety |
|
|||||||||||
|
|
· Separate cooking away from living area |
|
|||||||||||
|
|
· Washing and bathing facility |
|
|||||||||||
|
|
· Firefighting and first aid arrangement |
|
|||||||||||
|
|
· Disinfectant, fogging , anti-larva
frequency |
|
|||||||||||
|
|
· |
Crèche (if applicable) |
|
||||||||||
|
|
· |
Recreational Facility |
|
||||||||||
|
|
· |
Camp boss |
|
||||||||||
|
|
· |
Full time Scavengers |
|
||||||||||
|
|
· Full time Security guards |
|
|||||||||||
|
|
· Do’s & don’ts display and gender etc.
pictorial signage |
|
|||||||||||
|
26 |
EHS – Review |
|
|||||||||||
|
|
· EHS Performance Indicators, Monitoring
& Reporting to corporate office and client |
|
|||||||||||
|
|
· EHS Audit Schedule ( Internal &
External–TPA) |
|
|||||||||||
|
|
· EHS review – Self assessment |
|
|||||||||||
|
27 |
Reward & Recognition of workers &
staff |
|
|||||||||||
|
28 |
Personal Protective Equipment’s |
|
|||||||||||
|
|
· PPE identification & selection as per
function, hazard, usage & Indian Standard |
|
|||||||||||
|
|
· |
PPE reference matrix |
|
||||||||||
|
|
· PPE stock (minimum 20%) |
|
|||||||||||
|
|
· PPE issue, training, its usage &
maintenance |
|
|||||||||||
|
|
|
|
|||||||||||
|
29 |
All Inspection check list, Formats &
Reports |
|
|||||||||||
|
30 |
Emergency Preparedness Plan |
|
|||||||||||
|
|
· |
Objective |
|
||||||||||
|
|
· Identification of Emergencies and possible
scenarios |
|
|||||||||||
|
|
· Emergency control Channel and protocol
(Communication Flow chart) |
|
|||||||||||
|
|
· Role & Responsibilities of Emergency
Control Team/Evacuation Team/Administration |
|
|||||||||||
|
|
|
Team/Medical Help Team & other teams |
|
||||||||||
|
|
· Assembly locations, fire point, exit route
and display etc… |
|
|||||||||||
|
|
· Alarming the Emergency Situation &
Clearing off Emergency |
|
|||||||||||
|
|
· |
Mock drill frequency |
|
||||||||||
|
|
· Mock drill observation format |
|
|||||||||||
|
|
· Sharing / communication of outcome/
learning from the mock dill and preventive action plan. |
|
|||||||||||
|
|
|
|
|||||||||||
|
31 |
Safety Violation & Penalty Clause
(Penalty against safety violation for sub-contractors and employees) |
|
|||||||||||
Good Day Thanks.......